The Stratos Project
A proposed 9 GW data-center and natural-gas power campus on 40,000 acres in western Box Elder County.
A proposed 9 GW data-center and natural-gas power campus on 40,000 acres in western Box Elder County.
The public meetings described several large project numbers and several items that remain unpublished, pending, or not yet enforceable in the reviewed record.
Project area, nearby communities, roads, and affected lands. Click below to open the full interactive map.
Open the full mapFour comparisons show the scale: homes, emissions, gas, and water rights.
Enough generation for about 5.1M Utah-style homes. Utah has about 1.18M households.
No project-specific environmental-impact estimate has been published. A gas-power calculation at 60% capacity suggests roughly doubling Utah's current electric-power emissions, released from a project area about 35 miles from Brigham City.
About one Utah's worth of natural-gas demand. Utah plus Stratos would roughly double current statewide use.
About 4.24 billion gallons per year in contracted rights (= 13,000 acre-feet per year). Actual project demand has not been published.
This compares Stratos with the combined power capacity of every data center now operating in Utah.
The $108M / year figure is a full-buildout projection. The reviewed public record does not identify a clawback if jobs or revenue fall short.
If consent is granted, MIDA, not Box Elder County, becomes the land-use authority inside the project area for at least 50 years.
$108M / yr at full buildout. $30M / yr in Phase 1. Today, total countywide property tax: $76M / yr.
Plus an up-front $5.2-5.4M / yr × 3 yrs starting at the first building permit. (April 22 said $5.2M; April 27 said $5.4M.)
Three concessions reduce what the county would normally collect on a project this size.
92% reduction in the state energy-use tax rate for the project.
Data-center equipment fully exempt.
80% rebated to the developer. Only 20% flows to taxing entities.
The $108M / yr revenue claim is what's left after these concessions are applied.
"County revenue" is shorthand. Several taxing authorities normally receive a portion of property and energy-use taxes from a project this size:
In the reviewed public record, the $30M Phase 1 / $108M full-buildout figures describe what flows specifically to Box Elder County after MIDA's distribution rules and the tax cuts above are applied. The exact distribution to each entity depends on the final interlocal agreement, which has not been signed.
Eighteen questions raised by Box Elder County commissioners in the April 22 and April 27, 2026 meetings, with the substance of the answers given. The summary below shows where the public record stands; click any question to expand the full exchange and link to its moment in the recording.
Watch the full meeting on YouTube →
Answer summary. The project is competing with other states. There is an opportunity to secure limited energy-generation technology. The timeline is driven by external competition and equipment availability.
Key point. Urgency is external, not based on local readiness.
Watch at 17:50 on YouTubeAnswer summary. No percentage was provided. Framed broadly as supporting national security and military systems.
Key point. Military role is not quantified.
Watch at 19:05 on YouTubeAnswer summary. Project will follow state environmental permitting. No specific emissions or pollution data presented.
Key point. Relies on regulatory process rather than defined impacts.
Watch at 20:55 on YouTubeAnswer summary. Preliminary due diligence done. Formal studies (environmental, traffic, etc.) not yet complete. Will occur during permitting.
Key point. Key studies are still pending.
Watch at 21:20 on YouTubeAnswer summary. Based on projected data center operations and potential manufacturing. Described as a conservative estimate.
Key point. Jobs are projections, not guarantees.
Watch at 22:55 on YouTubeAnswer summary. No detailed formula provided. Justified by projected revenue scale.
Key point. Lacks transparent calculation.
Watch at 23:50 on YouTubeAnswer summary. Standard property tax lag applies. Developer provides about $5M per year up front for the first 3 years.
Key point. Up-front payments offset delayed tax revenue.
Watch at 25:55 on YouTubeAnswer summary. MIDA has land-use authority. County participates through the development review committee.
Key point. Shared process, but MIDA retains primary authority.
Watch at 36:55 on YouTubeAnswer summary. Future studies will determine impacts. Possible mitigation measures (buffers, coordination).
Key point. No concrete protections defined yet.
Watch at 37:45 on YouTubeAnswer summary. Natural gas is currently the only scalable option. Ruby Pipeline enables large-scale generation.
Key point. Decision driven by feasibility and scale.
Watch at 32:50 on YouTubeAnswer summary. Revenue tied to energy consumption. Assumes continued high demand.
Key point. No downside scenario clearly addressed.
Watch at 39:55 on YouTubeAnswer summary. Project described as locally managed with MIDA. No detailed clarification of state control.
Key point. Level of state influence remains unclear.
Watch at 48:05 on YouTubeAnswer summary. Developer pays for infrastructure up front. Infrastructure transferred to the county later.
Key point. Long-term maintenance becomes public responsibility.
Watch at 50:20 on YouTubeAnswer summary. County expected to provide services. Possible supplemental arrangements.
Key point. Ongoing costs likely shift to county.
Watch at 52:25 on YouTubeAnswer summary. No enforcement mechanism described. Confidence based on expected demand.
Key point. No guarantees or penalties outlined.
Watch at 59:45 on YouTubeAnswer summary. Acknowledged as oversight. Attributed to fast-moving process.
Key point. Transparency issue confirmed.
Watch at 43:20 on YouTubeWatch the full meeting on YouTube →
Answer summary. Developer provides about $16M over 3 years (about $5.2M/year).
Key point. Up-front funding exists, adequacy uncertain.
Watch at 26:46 on YouTubeAnswer summary. Future tax revenue expected to fund infrastructure. No detailed plan provided.
Key point. Relies on projected revenue rather than defined strategy.
Watch at 28:01 on YouTubeEvery number on this page traces back to a public source. Meeting-derived facts link directly to the moment in the YouTube recording. Federal and state numbers link to the agency dataset. Estimates show their math. If a number isn't on this list, it isn't on the page.
Every estimated number on this page is built from these inputs. Each topic-specific source group above (Power, Emissions, Gas, Water) shows the full step-by-step arithmetic for its derived figures.
GW × 8,760 hr × capacity factor = TWh/yr. So 9 GW × 0.6 × 8,760 ≈ 47.3 TWh/yr.