Scale, in everyday units

The same project, four ways.

Four comparisons show the scale: homes, emissions, gas, and water rights.

How much electricity?

~4×

Enough generation for about 5.1M Utah-style homes. Utah has about 1.18M households.

How much environmental impact?

~2×

No project-specific environmental-impact estimate has been published. A gas-power calculation at 60% capacity suggests roughly doubling Utah's current electric-power emissions, released from a project area about 35 miles from Brigham City.

How much gas?

+105%

About one Utah's worth of natural-gas demand. Utah plus Stratos would roughly double current statewide use.

How much water is tied up?

4.24BGAL/YR

About 4.24 billion gallons per year in contracted rights (= 13,000 acre-feet per year). Actual project demand has not been published.

Scale check

How large would Stratos be?

This compares Stratos with the combined power capacity of every data center now operating in Utah.

  1. Average existing Utah data center · 48 facilities running today~20 MW
  2. All operational Utah data centers, combined · 48 facilities920 MW
  3. Stratos Phase 1 · proposed3 GW
  4. Stratos full buildout · proposed9 GW
Phase 1 ≈ 3× the entire current Utah industry. All 48 Utah data centers running today add up to about 920 MW. Stratos Phase 1 alone (3 GW) would be more than that. Full buildout (9 GW) would be nearly 10× the entire current Utah industry. It would be added on top of Utah's grid, not drawn from it.